TSTC Harlingen New Tech Building

19%

Status

Planning [Planning portion of the project. ]

19% complete, updated on Thu 2/6/25 4:37 PM by Joseph Aguilar

Changed Status from Initiating to Planning.
Changed Percent Complete from 17% to 19%.
Uploaded Image (Thumbnail)Harlingen New Technology Construction Update

Work in Progress:

  • Structural steel erection complete.
  • Second floor elevated concrete slab has been poured.
  • Roof joist installation 80% complete.
  • Roof decking in progress.
  • First floor concrete slab on grade is 50% complete.
  • The project is within budget and tracking to be completed on schedule at this time
Project Details:
  • 84,600 Square Feet
  • Total Project Cost: $40M
  • Construction Cost: $32M
  • 2-Story, Concrete Tilt Wall Building
  • Programs: Automotive Technology and Diesel Equipment Technology
Meetings:
  • 02/17/2025: TSTC Harlingen CCAP
Milestones:
  • Construction Complete: 05/2025
  • Move In/Project Close Out: Fall (August) 2025

Details

Dates
Mon 11/11/24 - Wed 12/31/25
Acct/Dept
Employee
Type
Solutions Project Management / Construction
Health
Green - On track
Created
Fri 11/15/24 9:04 AM
Modified
Thu 2/6/25 4:37 PM

Project Request Form

Requestor
This is an individual that is listed as the person asking for a project evaluation, may not necessarily be the Project Champion.
TBD
Requested Delivery Date
Enter an estimated date you would like this project completed/delivered
12/31/2025
List your primary requirements for this solution.
Please list your primary requirements for this solution.
tbd
Please list any subject matter experts who can assist with this project.
Who has the knowledge in your area or other areas that can assist?
tbd

Manager