Executing [Implementation of the project]
41% complete, updated on Thu 2/6/25 3:57 PM by Joseph Aguilar
- Roof installation, exterior framing, and wall sheathing complete.
- Storefront and window installation 85% complete.
- Waterproofing nearly complete.
- HVAC rooftop units installed on 12/18/2024.
- MEP rough-in 90% complete.
- Fire sprinkler installation early complete.
- Interior framing and drywall in progress.
- The project is currently on schedule and within budget overall.
Project Details
- 52,800 Square Feet
- Total Project Cost: $30.3M
- Construction Cost: $21.5M
- 1-Story, Pre-Engineered Metal Building
- Programs: Diesel Equipment Technology, Electrical Lineworker Technology, HVAC Technology, and Plumbing & Pipefitting Technology
Meetings
- 02/11/2025: Discussing OIT Computers & AV Needs
- 02/19/2025: TSTC CCAP Meeting
Milestones
- Construction Complete: June 2025
- Move In/Project Close: Out Fall (August) 2025