TSTC Abilene Building

41%

Status

Executing [Implementation of the project]

41% complete, updated on Thu 2/6/25 3:57 PM by Joseph Aguilar

Changed Status from Planning to Executing.
Changed Percent Complete from 36% to 41%.
Uploaded Image (Thumbnail)
CCAP Abilene Construction Update 

Work in Progress:

  • Roof installation, exterior framing, and wall sheathing complete.
  • Storefront and window installation 85% complete.
  • Waterproofing nearly complete.
  • HVAC rooftop units installed on 12/18/2024.
  • MEP rough-in 90% complete.
  • Fire sprinkler installation early complete.
  • Interior framing and drywall in progress.
  • The project is currently on schedule and within budget overall.
Project Details
  • 52,800 Square Feet
  • Total Project Cost: $30.3M
  • Construction Cost: $21.5M
  • 1-Story, Pre-Engineered Metal Building
  • Programs: Diesel Equipment Technology, Electrical Lineworker Technology, HVAC Technology, and Plumbing & Pipefitting Technology
Meetings
  • 02/11/2025: Discussing OIT Computers & AV Needs
  • 02/19/2025: TSTC CCAP Meeting

Milestones
  • Construction Complete: June 2025
  • Move In/Project Close: Out Fall (August) 2025

Details

Dates
Sat 6/1/24 - Fri 9/12/25
Acct/Dept
Employee
Type
Solutions Project Management / Construction
Health
Green - On track
Created
Fri 11/8/24 8:37 AM
Modified
Thu 2/6/25 3:57 PM

Project Request Form

Requestor
This is an individual that is listed as the person asking for a project evaluation, may not necessarily be the Project Champion.
TBD
Requested Delivery Date
Enter an estimated date you would like this project completed/delivered
11/30/2025
List your primary requirements for this solution.
Please list your primary requirements for this solution.
TBD
Please list any subject matter experts who can assist with this project.
Who has the knowledge in your area or other areas that can assist?
TBD

Manager