TSTC Abilene Building

28%

Status

Planning [Planning portion of the project. ]

28% complete, updated on Thu 12/19/24 3:30 PM by Joseph Aguilar

Uploaded Image (Thumbnail)

Uploaded Image (Thumbnail)

The Abilene project is currently under construction.

The construction crews are working on installing windows, storefronts, overhead plumbing and insulation. Gas is 100% inside the building but not connected to any equipment. Crews will need to work on building runs outside of the building so that they can terminate them.  

The crews have been working on the SWPPP inspections as well as reviewing and testing the concrete & rebar

The project team should deliver a schedule update by mid to late January or early February. 

Craig would like to have equipment in the MDF/IDF by May 2025

Construction Installs:

  • Offices Set Up By: June
  • Completion Date: July 17, 2025
  • Ready Date: First Day of Class Fall Semester 2025

Details

Dates
Sat 6/1/24 - Fri 9/12/25
Acct/Dept
Employee
Type
Solutions Project Management / Construction
Health
Green - On track
Created
Fri 11/8/24 8:37 AM
Modified
Thu 12/19/24 3:30 PM

Project Request Form

Requestor
This is an individual that is listed as the person asking for a project evaluation, may not necessarily be the Project Champion.
TBD
Requested Delivery Date
Enter an estimated date you would like this project completed/delivered
11/30/2025
List your primary requirements for this solution.
Please list your primary requirements for this solution.
TBD
Please list any subject matter experts who can assist with this project.
Who has the knowledge in your area or other areas that can assist?
TBD

Manager