Executing [Implementation of the project]
19% complete, updated on Thu 2/6/25 5:01 PM by Joseph Aguilar
- Concrete tilt wall panels built and ready to be erected.
- Due to unstable soil within the crane path, the crane for tilt wall panels was not able to be mobilized as planned in December. Soil was remediated over the holiday break, and the crane has now been mobilized.
- Tilt wall erection scheduled for early January, and should take 2 weeks to complete.
- Structural steel deliveries begun.
- The project is currently within budget. The soil remediation requirements for the crane path will likely impact the construction completion dates. Spring 2026 opening will not be affected
Project Details:
- 129,120 Square Feet
- Total Project Cost: $70.4M
- Construction Cost: $59.7M
- 2-Story, Concrete Tilt Wall Building
- Programs: Building Construction Technology, Electrical Construction, Solar Energy Technology, Plumbing & Pipefitting Technology, and HVAC Technology
Meetings:
- 02/19/2025: TSTC CCAP OAC
Milestones:
- Construction Complete: September 2025
- Move In/Project Close Out: Spring 2026