Planning [Planning portion of the project. ]
41% complete, updated on Thu 12/19/24 3:46 PM by Joseph Aguilar
Changed Percent Complete from 39% to 41%. TSTC EWCHEC Hutto Building projects Building 2 is currently in the design phase construction documents should be coming out the week after Thanksgiving, the first week in December 3rd Floor Reno: Today the team discussed the removal of some office spaces, increased the conference room size, floor plans for the 1st & 2nd floor, ceiling plans, the XR room (adjustments to better use the space), dumpster enclosure, exterior & interior finishes and next steps. Construction Installs: Building # 2 - No date yet 3rd Floor Reno Construction Begins: January 20, 2025 Construction Completion: June 30, 2025 Furniture & Equipment Move-In: July 21, 2025 Occupancy: August 15, 2025
TSTC EWCHEC Hutto Building projects