TSTC EWCHEC Hutto Building

41%

Status

Planning [Planning portion of the project. ]

41% complete, updated on Thu 12/19/24 3:46 PM by Joseph Aguilar

Changed Percent Complete from 39% to 41%.

TSTC EWCHEC Hutto Building projects

  • Building 2 is currently in the design phase construction documents should be coming out the week after Thanksgiving, the first week in December
  • 3rd Floor Reno: Today the team discussed the removal of some office spaces, increased the conference room size, floor plans for the 1st & 2nd floor, ceiling plans, the XR room (adjustments to better use the space), dumpster enclosure, exterior & interior finishes and next steps.

Construction Installs:
  • Building # 2 - No date yet
  • 3rd Floor Reno
    • Construction Begins: January 20, 2025
    • Construction Completion: June 30, 2025
    • Furniture & Equipment Move-In: July 21, 2025
    • Occupancy: August 15, 2025

Details

Dates
Thu 6/13/24 - Thu 12/31/26
Acct/Dept
Employee
Service
Project Request and Analysis / Project Request
Type
Solutions Project Management / Default
Health
Green - On track
Created
Thu 10/3/24 11:23 AM
Modified
Thu 12/19/24 3:46 PM

Project Request Form

Requestor
This is an individual that is listed as the person asking for a project evaluation, may not necessarily be the Project Champion.
Jay Wesson
List your primary requirements for this solution.
Please list your primary requirements for this solution.
Obtain and install all end user hardware.
Please list any subject matter experts who can assist with this project.
Who has the knowledge in your area or other areas that can assist?
Joseph Aguilar, Lance Rivera

Manager

Alternate Manager(s)

Sponsor