Planning [Planning portion of the project. ]
65% complete, updated on Fri 11/22/24 5:07 PM by Janine Reneau
Changed Percent Complete from 45% to 65%. Abilene, Harlingen, and Waco locations are installed, configured and online. Breckenridge and Brownwood will have All-In-One's mounted for Kiosk at each location. Waiting for equipment and mounting so that OIT may install software and configure. Marshall and NTX were installed by Physical Plant this week and are now ready for configuring by OIT. Sweetwater is still needing electrical by Physical Plant. OIT will meet with Cory from Temple College and Steve from Agile Fleet on Monday to troubleshoot connectivity. Training will begin on Dec 3rd for Fleet Team and Admins. Training to campuses will be a phased approach. Working with C&CS for announcing roll out. Go Live will be in January 2025