Monitoring & Controlling [Testing and Validation of Requirements]
87% complete, updated on Thu 2/6/25 4:51 PM by Joseph Aguilar
- All final inspections passed. Certificate of Occupancy issued by the City of Waco.
- Contractor nearing completion of Owner/Architect punch list.
- TSTC IT network complete and active. AV and computer installation scheduled for this month.
- Furniture and equipment move on-going, with Region 12 complete and remaining from TSTC scheduled for early January.
- The project is currently within budget and on schedule.
- Close out and turnover documents are being gathered and owner trainings are scheduled for early January
Project Details:
- 30,047 Square Feet
- Total Project Cost: $17M
- Construction Cost: $12.4M
- 1-Story, Concrete Tilt Wall Building
- Workforce and Dual Credit Training
Meetings:
Milestones:
- Construction Complete: January 2025
- Move In/Project Close Out: Spring (February) 2025
- Close Out Document/Building Transfer: Signed Monday February 3, 2025